Methods of Dispute Resolution
29th March 2019
- Project within a project
Negotiation
- preferred; cheapest (most cost-effective)
- investment/value balance (i.e. worth it?)
- cost of winnings / cost of losings (Cost-Benefit Analysis)
- "Matter of Principle" not good enough reasons
- Even at Negotiation, you can bring lawyers to negotiate on your behalf
Varying Levels of "Binding"
- some disputes are contractual (mechanism decided in the contract)
- some are governed by statute
Courts are expensive and time-consuming
- expert witnesses, barristers, solicitors etc.
- procedurally driven, public, formal
Business reasons for keeping matters non-public
Improve or limit damage to relationships
Control over resolution diminishes down the list (on slide) (negotiation to arbitration)
Recording in writing any agreement, even "provisional" and "informal" matters
Silence in a dispute is a rejection
- remember the factors that indirectly influence the tribunal
- has to be silent for a reasonable time, i.e. in relation to the case
Difference between Mediation and Conciliation
- conciliator gives a view
- mediator doesn't give a view
- patience and other soft skills necessary for a mediator
- people in attendance need to be in authority to decide
Neutral Evaluation
- how Different to Mediation?
- a third party deciding whereas a mediator is helping the two parties to negotiate and reach a solution together (non-binding and only an opinion)
- maybe about the 'expertise'
Expert Determination
- only binding on the authority he/she is appointed for (extension of time vs compensation of extra costs e.g.)
- use his own expertise without revealing how (different to Adjudication)
Dispute Resolution Boards
- contract mechanism (i.e. consensual)
- large contracts, very expensive procedure
Adjudication
- Housing Grants, Construction & Regeneration Act 1996 (essential for us architects)
- invented for small disputes, but not the case anymore
- s108(2) prevents a limit to make a dispute
- no limitation on time or kind of dispute
- decision-making is time-driven; quick
- Adjudicator appointed by RIBA (?)
- based on evidence presented to him/her (evidence, not expertise), if he/she has expertise they can point the parties in the right direction
- temporally binding, can restart disputes
- all about helping cash-flow through the industry
- broken Natural Justice; like not given the other side chance to give evidence
- Limits of Disputes: jurisdiction of adjudication (EXAMPLES?)
- tends to benefit the party who wants to be paid
Arbitration
- private
- most common dispute resolution
- procedure has to be in writing
- biggest advantage to litigation is privacy
- S BC/Q2016; Litigation is default, not Arbitration
Litigation
- public
- court
- controls & restrictions
- parties lose control
- different courts and varying levels of cost and controls (represent yourself etc.)
Adjudication is standard, then either Arbitration or Litigation
Documentation
Architect's Letters, Instructions, etc. (Communication)
Letters (evidence)
Agendas/Minutes (evidence)
Instructions
Notes, records, internal memos
Notices & Certificates
Wording
Capitalised words = meaning in contract
Italicised (NEC 4) = further description
Some times email is not an acceptable form of communication in the contract/appointment
Letter to a prospective client
- clear and concise
- link to website
- don't mention fees
- stay in control of plan of action, next steps
Letter to contractor on behalf of client
- after Offer of Acceptance
- authority to bind client in contract
- draft it and make them send it
Contractor communication should be concise, direct and to the point
Meetings
- Examples
- Design
- Pre-start
- Progress meeting
- Purpose
- Outcomes
- Agenda
- Minutes (not Contractor's Documents)
- Record
- Issued - if unchallenged = approved
- Means of Communication
- File-sharing
- Protocol
- Health&Safety
- Insurance (evidence/proof)
Contracts
Sections - areas of work
- dates
- liquidation of damages
- start
- completion
CAI (Contract Admin Instruction)
- issue an instruction and a variation
- can't alter the terms of the contract, only act within them
- would need a deed of variation to the contract
- not necessary to draft a new contract
Reduction of Scope of Works
Adjust the Specification
Issue a Variation
Domestic Sub-contractor is taken responsibility of by the Main Contractor
Don't attach the quotation to an Instruction - add Terms & Conditions
Carry the risk by issuing an instruction and variation to the spec - think ahead
task 6 - Recorded in writing, not just as a variation
Notice (-> received)
Certificates (issued ->)
- never issue a certificate unless you are contractually obliged to
Letter of Intent
JCT SBC/Q Payment - Background
Payment regime in SBC
5 days after DUe Date can't change
7 days before final date can change
Contract conditions of paying on an invoice or a certificate
No negative payments i.e. payments can't go both ways in SBC, but can do in NEC
"Days" means "Calendar Days"
Omit previous work in Certificate
My job to tell the QS if the work is in accordance with the contract
Who owns material? Not fixed and clear idea until it is fixed to the ground
Retention of Title Clauses, if you don't own materials you can't pass them on
The only one who can issue a pay-less notice is the Employer (in general) or Contractor in the Final Certificate