Procurement & Building Contracts

12th April 2019 - Sarah Lupton

Nature of Client

Governmental intervention for public good/protection (regulations)

Trialing for new procurement routes

Partnering: to increase efficiency and reduce disputes

- government driven to waste less time and money (Latham Report)

- https://www.designingbuildings.co.uk/wiki/Latham_Report

Must include specific info on payment and adjudication (Housing Grants, Construction & Regeneration Act 1996)

- impacts all clients, unless residential occupier

Public Sector - Public Contract Regulations

Domestic/Consumer - Consumer Rights Act

Client Preference

Existing

Single point responsibility?

Cost-Time-Quality

Banks? Funding? Cash flow and stake holders, Brexit

Risk scope

Procurement Route preferred

Two-party (various versions within)

- D-B-B (traditional) (client supplies design)

- D&B (contractor supplies design)

- MGMT

Multi-party

- Project team agreement/supplemental provisions

- suggests collaboration

Contractor supply chain (sub-contractors)

Tendering

- at the end of Stage 4 (D-B-B)

- between 2 and 3 (locked in?) D&B one-stage

- twice (PCSA, not responsible for design at first) D&B two-stage

Problematic keeping the same contractor, “foot through the door”, budget out of control

Can do D&B without Novation

- more Appointment issue, not Procurement

Example: Change of Architects during the project

Stage 1 and 2 (architect A)

Stage 3 and 4 (architect B)

Stage 5, 6 and 7 (architect C)

- concept architect>technical architect>delivery architect

Management

- Contract Manager to oversee all the contracts that exist between the Client and the Client-selected/appointed Contractors (more than one)

- each package has its own cycle of tendering

Alliancing

- Board of Directors behind the scene

- Large projects

- Shared risk & reward (insurance)

- pay&gain mechanism

- collective goals

- no-claim-clause

- panels checking before (because of risk)

Project Profile

- matching Client’s needs

Bespoke

- based on Standard form

Lawyers comfortable with JCT because they are used to them

ACA - PPC2000 (Project Partnering Contract)

D&B - turnkey

- handed over: operational (power plant e.g.)

Constructing Excellence

- form that can be set up between any two parties involved

JCT HO

- small projects

- short contract

- e.g. a house

D&B

- Contractor doesn’t take liability in mistakes in any design (might be desirable from the Employer’s point of view)

Liability

Guaranteeing performance criteria

ER provided to tender, Contractor gives his Contractor’s Proposal (CP)

Sub-Contractor liability

- collateral warranty to protect the Client

- balance risk

Design

- ?

TIme

- ?

Cost

- cost-plus: when it’s hard to judge, feeding drawings ad hoc

Contract Administration

12th April 2019 - Sarah Lupton

(JCT SBC - focus for this lecture)

Duties & Powers

Time

- Contract Dates

- Date of Possession

- Date of Completion

- Length of Contract - flaws and benefits

- Extensions

- list of events that are allowed to defer the Date of Possession

- sequence: only start some work when other work has started (i.e. the critical path)

- affect the Date of Completion?

Constructing Excellence

- most innovative form

- schedule of all parties, very clear (time & event)

- the parties all share the risk

CDP-(CP/ER) -> D&B -> SBC

Don’t override clauses, add unique ones

Clause 2.13.2 - crucial for Contractor

PC

Dimininus

Partial Possession (part of building which is completely finished)

Rectification Period (checking for mistakes)

- instruct remedial works

Cost

- Acceleration Quotation (Client wants to speed it up)

- Fluctuations Provisions (pay more or less if price changes, e.g. governmental, indices, tax, tarriffs) - risk allocation device

- Provisional Sum (adjusted later up or down)

- Quotation vs Instruction & Cost Assessment

- Cost Savings (issued by Architect’s Instruction)

- Instruction is ground for extension f time

Certification (Inclusions & Deductions)

- Housing Grants Act (Interim Certificates)

- risky paying for things before they have arrived on site

Don’t interfere whether Contractor gets paid or not

BIM-protocol (BIM + D&B?)

Previous
Previous

RIBA Building Contracts: Concise & Domestic

Next
Next

Practical Employment Law